Deep Foundations Specialist

 
 

  NEWS - February 2010

Retaining Walls
Temporary or Permanent

For basements, pools, lift-wells, cellars & site cuts

  Low vibration areas can be serviced with steel H beam “soldier” posts and treated pine sleepers.

The post hole is pre-drilled and the H beam pushed down as far as possible.

If further depth is required, small one second bursts of vibration are applied.

The sleepers are loaded into the H beams and pushed down as the soil is removed from the front of the wall.

  Steel sheet piles are hammered with a vibratory hammer carried by a 2.5m wide 20t excavator.

Vibration is minimized by pre-drilling the sheet location and a Seismic monitor and alarm are attached to nearby structures to warn of high vibration levels.
 

   

Contact Us for more info ....

  

  NEWS - March 2009

March 2009

Sheet Piling

Q-Pile took delivery of a new sheet pile vibratory hammer
which attaches to either our new narrow 20t excavator
or our standard 30t excavator.
 
The photos show a temporary retaining wall being installed
prior to excavation for a basement.
 
The sheets will be removed on completion of the basement.
 
We use a seismograph to monitor and record the ground and
nearby building vibrations; and an alarm unit alerts
the operator to excessive vibration.
 
Low establishment costs make those small jobs feasible.
 

Small Jobs Are Now Affordable !
  

$550 site establishment and
removal charge for a sheet piling
rig on the Sunshine Coast.
 
That’s all it costs for our narrow 2.5m
wide 20t excavator rig.

Contact Us for more info ....

 

  NEWS - October 2008


 

October 2008

1100t CRANE ON SCREW PILES

This 1100t crane and load is balanced on 4 concrete pads
that are sitting on screw piles
down 12m through soft soil onto the sandstone below.
 
The load is a 82m long, 184t bridge beam.
 
The concrete pads were monitored by a surveyor for settlement
during the lift and none was recorded.
 
Q-Pile was commissioned to urgently design and install the pads and piers.
 
This was achieved within 6 days from the initial phone call
to the completion of the concrete pour.

We had fantastic assistance from Russell Heale Engineering
and Rymark Engineers, together with on-site assistance
from the project team’s welders and concreters.
 
Contact Us for more info ....

 
 

  NEWS - March 2008


 

March 2008

Deep piers for a 10 level
building in Ann St, Brisbane

Early in 2008, Q-Pile was contracted to drill deep piers for a
10 level building in Ann St, Brisbane.
 
Holes up to 6.0m deep and from 600 to 1000 mm in diameter were
drilled into a siltstone material using a continuous flight auger driven
by a 50 kNm planetary drive unit mounted on a 30t excavator.
 
On hand was our maintenance van with welding facilities for hardfacing
the auger flights and for removing and replacing auger teeth.
 
Support excavators were on hand to remove the spoil and construct
pads for the drilling excavator to work from.
 
Contact Us for more info ....


  NEWS - December 2007

 

         
 

December 2007

2000 kN (200t) capacity screw piles
 
Q-Pile takes delivery of a new and faster drive unit
that is capable of installing 200t capacity piles.
 
This unit is coupled with Australia’s first 200 kNm
electronic load cell which accurately monitors
the installation torque which is the indicator
of the pile’s load capacity.
 
This unit will twist up and snap a 273mm diameter
pile of 6.4mm thickness with ease!
 
Contact Us for more info ....
 

Copyright
 Website Design MagicFormulaMarketing.com